Microsoft reduced spending by approximately $5 billion due to delays in data centers, while AMD raised its revenue forecast
According to a report by The Information, Microsoft has reduced its capital expenditures for the third quarter by about $5 billion due to delays in the third-party data center it plans to lease. Sources say that the data center project by Iren located in Childress, Texas, has encountered delays, leading Microsoft to postpone some expenditures. Microsoft had previously announced plans to invest $9.7 billion over five years to lease servers equipped with NVIDIA GPUs from Iren.
Power supply and grid access have also become bottlenecks for computing power delivery. Last month, Microsoft withdrew from a plan to lease a data center project in the UK from Nscale due to delays in grid access. As self-built data centers struggle to meet demand in a timely manner, Microsoft is simultaneously leasing computing power from multiple cloud service providers.
Meanwhile, AI server supplier Supermicro continues to raise its performance expectations. The company's revenue for the first fiscal quarter reached $19.95 billion, exceeding analysts' expectations of $16.39 billion, and it expects revenue for the second fiscal quarter to be between $19.5 billion and $21.5 billion. The revenue forecast for fiscal year 2027 has also been raised from $65 billion to $72 billion to $72 billion to $82 billion. Bernstein pointed out that assessing AI computing power demand cannot simply rely on contract amounts or megawatt scale; it also needs to consider contract cancelability, duration, and actual deployment time; some projects may be delivered in phases, and chip procurement agreements may correspond to the same batch of computing power as data center leasing contracts.