SK Hynix is advancing the expansion of HBM4 production capacity, with the goal of having equipment enter the factory in the first half of next year
According to Electronic News on November 15, SK Hynix is discussing the procurement orders for HBM4 manufacturing equipment with partners, mainly involving the procurement timeline and quantity of post-processing equipment such as bonding, cutting, and testing. Sources familiar with the partners stated that the company is advancing additional investments in HBM4 production equipment, aiming to complete the equipment's arrival and installation in the first half of next year, with some equipment required to be delivered before the first quarter.
The additional production base is likely to be Cheongju P&T6. This plant was previously known as M8, and SK Hynix designated it as an HBM production base in 2025, starting the construction of HBM manufacturing lines earlier this year. Industry insiders stated that the company plans to utilize the idle space in P&T6 to expand HBM4 capacity, which could produce more than 20,000 additional HBM wafers per month at full capacity. SK Hynix mentioned in last month's third-quarter earnings briefing that the supply of DRAM and HBM for the next three years until 2029 has essentially been sold out. Company insiders stated that they have been continuously placing equipment orders according to their plans and will respond to market expansion.